Security screens, stage by stage: what actually happens on the day.
The measure takes 20 to 40 minutes. The written quote lands within two business days. Manufacture is 1 to 3 weeks depending on the season. On installation day one installer takes 45 to 90 minutes per hinged door, 1.5 to 2.5 hours for a sliding security door and 15 to 25 minutes per window screen, so a typical two-door, six-window Wollongong house is a 3.5 to 6 hour job. No water needed, one power point is plenty, and the only thing we really need from you is somewhere to park.
Most people have never had screens fitted before and the questions are always the same: how long will you be here, do I need to take the day off, what about the dog, and what does the place look like when you leave. Here is the honest version, stage by stage, with the things that stall a job called out where they happen.
The full timeline, measure to handover
Times are for one installer on a single-storey house with normal access. Add roughly 30 per cent for a second storey, a steep block or a unit with stairs and no lift.
| Stage | How long | What happens | What you need to do |
|---|---|---|---|
| 1. Free measure | 20 to 40 min | Every opening measured in three places, frame type checked (aluminium, timber or steel), distance from the water assessed, mesh grade and hardware recommended. | Be home, unlock the side gate, and know which openings matter to you. Point out any window you want left as a fire escape. |
| 2. Written quote | Within 2 business days | Itemised opening by opening, naming the mesh grade, coating, lock type and fixings, with the warranty terms attached. | Read it against the other quotes on the same five line items. Ask for changes before you accept, not after. |
| 3. Accept and order | Same day you accept | Measurements go to fabrication and a fitting date is booked. A deposit covers materials, with the balance due on completion. | Confirm colour and handing (which side the hinges go, which panel of the slider opens). Both are hard to change later. |
| 4. Manufacture | 1 to 3 weeks | Screens built to your exact openings. Off-peak, roughly May to August, it is 1 to 2 weeks. From October to Christmas it stretches to 3 or more. | Nothing. This is the good time to book a day at home or arrange for someone to be there. |
| 5. Arrival and set up | 10 to 20 min | Van arrives between 7:00am and 8:30am, panels unloaded and stood against a wall, drop sheets down, a quick walk-through of the openings with you. | Have a parking space clear, pets contained, and the openings clear inside and out. |
| 6. Hinged security door | 45 to 90 min each | Old door removed, reveal checked for square, frame fitted and packed, 8 to 14 one-way screws into the reveal, hinges hung, lock and egress release fitted and aligned. | Stay clear of the doorway. The door will be open to the weather for most of that time. |
| 7. Sliding security door | 1.5 to 2.5 hours | Track cleaned or replaced, rollers set, panel hung and adjusted, hook-bolt lock fitted and the whole thing run in until it glides with one finger. | Clear the outdoor furniture and the mat. The back opening will be unusable while it is out. |
| 8. Window screens | 15 to 25 min fixed, 25 to 40 min hinged egress | Old flyscreen out, reveal cleaned, screen offered up and packed square, one-way screws through the frame, egress screens get hinges and a quick-release catch tested from inside. | Clear the sill and pull curtains and blinds fully back. Move anything breakable out of the room. |
| 9. Extras | 30 to 90 min | Pet door into a screen door is 30 to 45 minutes. A retractable flyscreen is 60 to 90 minutes because the cassette has to be dead plumb. | Keep the pet away until the flap is fitted and the surround has set. |
| 10. Clean up and handover | 20 to 30 min | Vacuum and magnet sweep for swarf, drop sheets up, every lock and latch tested, keys handed over and keyed alike if ordered, egress releases demonstrated to whoever is home, warranty and care sheet handed over. | Walk every opening with the installer and open and close each one yourself before you sign off. |
| 11. Settling adjustment | 1 to 4 weeks later, if needed | Timber jambs move with humidity, and a hinged door occasionally needs the latch nudged after the first wet week. That visit is free. | Ring it in as soon as the latch feels tight rather than forcing it. |
Typical mid-tier Wollongong house, two doors and six windows: 3.5 to 6 hours on site, one visit. Costs for each item are on the pricing page.
Prepare-for-the-crew checklist
Ten minutes the night before saves half an hour of labour on the day. Tick these off, print it, or leave it on the kitchen bench for whoever is home.
Access and parking
Inside the house
Pets, kids and working from home
Before we leave
Want a fitting date before the summer rush?
Lead times run 1 to 2 weeks over autumn and winter and stretch past 3 weeks from October. Book the measure now and pick your day.
Access, parking, power and water
Parking is the single thing that most often costs time. A hinged door panel is about 2 metres tall and awkward rather than heavy, and a sliding door panel is worse. Carrying one 60 metres from a parked van, past a neighbour’s car and through a side gate, adds up across a whole house. A driveway space or a kerbside spot outside the front door is worth more to the job than anything else you can do. The older pockets of Corrimal, Fairy Meadow and Gwynneville have narrow streets and a lot of on-street parking, and the CBD unit blocks often have no visitor bay at all, so mention it at the measure and we plan around it.
Power is nice but not critical. Most fabrication happens off site, so the day is mostly cordless drills, a vacuum and occasionally a drop saw for a trim cut. One standard 10 amp outlet, inside or out, covers everything. We do not need water, although an outside tap is handy for washing hands and rinsing masonry dust off a path. Nobody needs to disconnect anything, and there is no need to be off the internet or off the power at any point.
Noise, dust and smell
Noise comes in bursts, not a steady roar. Every fixing into a brick or rendered reveal is a 10 to 30 second run of the hammer drill, and a hinged door needs 8 to 14 of them. Between openings it is quiet talk and hand tools. In practice a whole house is maybe 15 to 20 minutes of genuinely loud work spread over five hours. New South Wales noise regulations restrict power tools at residential premises to daytime hours, generally not before 7:00am and not after 8:00pm on weekdays and Saturdays, and not before 8:00am on Sundays and public holidays. We do not start drilling before 7:30am out of courtesy to your neighbours regardless.
Dust is fine masonry powder at each fixing point and metal swarf where anything is trimmed. Both are managed with a drop sheet under the opening and a vacuum before we move on. The one to watch is swarf walked into a light carpet or a timber deck, which is why we magnet sweep at the end. Smell is silicone: most exterior sealants cure by releasing acetic acid, so the house smells faintly of vinegar for a few hours. Leave a window open and it is gone by evening.
Pets, kids and working from home
Every door we work on stands wide open for the duration. Cats get out, and a dog that would never normally leave the yard will follow a stranger to the van. Put them in a closed room, in the car with someone, or at a neighbour’s for the morning. If the dog is anxious around power tools, tell us and we will do that side of the house last.
Children need to be out of the work zone rather than out of the house. Cut mesh edges, offcuts of aluminium and dropped screws are the hazards, and none of them look dangerous to a five year old. Working from home is completely workable: give the installer your call times when they arrive and they will schedule the drilling around them. A whole house is only a handful of genuinely loud windows.
Weather, and what actually stops a job
Wollongong weather stops fewer jobs than people expect, because most openings on most local houses sit under an eave or a verandah. Light rain is not a problem there. What does stop us is persistent rain, because exterior sealant will not cure properly against wet masonry and the reveal has to be dry when the frame goes in. An east coast low, the sort that parks over the Illawarra for two or three days, is a reschedule. So is a strong wind: a 2 metre panel is a sail, and handling one on an exposed site in a hard north-easter or a winter westerly funnelling down off the escarpment through Figtree and Mount Ousley is not safe.
A reschedule costs you nothing and we normally slot you back in within a week. The other delay worth knowing about is upstream: if a mesh colour or a hardware item is on back order, that shows up during manufacture, not on the day, and you will hear about it before your fitting date rather than after.
What a clean site looks like, and where the waste goes
When we leave, every drop sheet is up, the swarf is vacuumed and magnet swept, the masonry dust is off the sill and the path, the packaging is in the van, and the old doors and screens are gone unless you asked to keep them. Nothing should be leaning against the fence and there should be no screws in the lawn. If a light-coloured path has picked up a smear of drilling dust, it hoses off.
Old aluminium frames and stainless mesh are scrap metal with real value, so they go to a metal recycler rather than to landfill. Fibreglass insect mesh, rubber spline, old rollers and packaging foam are not recyclable and go to general waste. If you are clearing out old screens yourself before we come, Wollongong City Council’s waste and resource recovery facility at Whytes Gully in Kembla Grange takes household metal and general waste, and scrap yards around Unanderra and Port Kembla will take clean aluminium.
The honest part: when the day does not go to plan
Three things stall a job, and all three are avoidable. First, an out-of-square reveal in an older house. Weatherboard and fibro homes around Corrimal and Coniston can be 8 to 10 mm out over a door height, which we pack and scribe on the day, but it adds 20 to 30 minutes per opening. Second, a rotten or split timber jamb that only shows itself when the old door comes off. We will not screw a security frame into soft timber, so that opening gets deferred until the jamb is repaired, and we will tell you what it needs. Third, someone changing their mind about handing or colour on the day. Made-to-measure screens cannot be flipped, so that is a re-order and a second visit.
We would rather leave one opening undone and come back than fit a screen into something that will not hold it. If you would rather handle the install yourself, the DIY versus professional page sets out exactly what that involves, and how to choose a door covers what to settle before the order goes in.
Installation day questions
How long does a security door installation take in Wollongong?
What do I need to move before the installers arrive?
How noisy and messy is the day?
Do you need power, water or parking?
What happens if it rains on installation day?
What happens to the old doors and screens?
Book the measure and pick your installation day
Send your suburb and the openings you want done. We measure on site, quote within two business days, and give you a firm fitting date when you accept.
Before the day, settle two things
Know how many openings you actually need, and know exactly what the warranty covers once the installer drives away.